Seventh Tee Construction
Spring of 2005
The G&G department has a habit of disposing of good material where a future tee might be needed.
The Poplar tree next to the blue tee needed to be removed for the new back tee and for the fact that its roots were ruining the tee next to it.
We pushed the dumped material over to the desired location.
Shaped up the tee.
December 2006
It was now time to resurface and level the rest of the tees on this hole. However, what started out a a small tee project and a small drainage project right next to each other had combined to be a large, wet project.
We manage to install some good drainage and dry it out and get it shaped and sodded. The last few thousand square feet will be done in the spring.
We leveled and shaped the forward tee as well.